Hansen Elementary School | ||
Construction Cost Estimate | ||
1/13/2015 | ||
Architect/Engineering | $250,000 | |
Construction costs | $3,599,900 | |
Soft Costs | $94,000 | |
Furn. Fixtures and Equipment | $58,000 | |
Remove/Disposal Existing Modulars | $70,000 | |
Contingency | $275,000 | |
Total Project Costs | $4,346,900 | |
Less Architect/.Engineering (Prev. Funded) | -$250,000 | |
Funding Request | $4,096,900 | |
Rounded to | $4,100,000 | |