This is a reminder to all Canton voters that last month's Annual Town Meeting voted to place the proposed 8-room addition at the Hansen Elementary School on the ballot for a debt exclusion override vote. The election will take place on Tuesday, June 23rd. The projected cost for the project is $4.1 million.
Here's a breakdown of the projected costs for the project:
Hansen Elementary
School Construction Cost Estimate 1/13/2015
Architect/Engineering $250,000
Construction costs $3,599,900
Soft Costs $94,000
Furn. Fixtures and Equipment $58,000
Remove/Disposal Existing Modulars $70,000
Contingency $275,000
Total Project Costs $4,346,900
Less Architect/.Engineering (Prev. Funded) -$250,000
Funding Request $4,096,900
Rounded to $4,100,000